Final Inspection: Sitio Electrification Program (SEP) 2021
11/14/2022
date posted
The Final Inspection and Acceptance activity of the completed/energized sitios under the Sitio Electrification Program (SEP) for the year 2021 has started earlier today and shall be continued for the rest of the week.
The activity is being facilitated by visitors from the Total Electrification Division of the National Electrification Administration and assisted by the Technical and Institutional Services Departments of SURSECO-I.
The Final Inspection marks the total completion of the successful implementation and energization of the eighteen (18) sitios across SURSECO-I's coverage area under the 2021 SEP GAA Subsidy.
SURSECO-I continues to extend its gratitude to NEA, the National Government, LGUs, and Barangays for the usual and unending support for the success of the project implementation.
We hope for more SEP projects in the future to continue bringing brighter homes in the countryside.
|
c2ecc095-88b5-759c-c0fd-3a05334f3637
|
BASD Maintenance Activities
09/09/2022
date posted
The Operation and Maintenance Section of Barobo Area Services Department successfully conducted the pole relocation and replacement of damaged pole at Sta. Cruz 2, Tagbina yesterday.
Power in the affected areas was restored at 4PM which was earlier than scheduled.
Thank you linemen!
|
c2ecc095-88b5-759c-c0fd-3a05334f3638
|
CSIS Line Activities
09/08/2022
date posted
The Construction and System Improvement Section has started the relocation works of poles affected byt the DPWH Road Widening Project at Bislig Bridge, Catanduan, Poblacion, Bislig City.
Earlier today, the team facilitated hole digging and pole erection. The whole activity will undergo for a few weeks and a power interruption is expected during the relocation of the primary lines.
Keep safe, team!
|